City: Northern Jordan Valley Project Goal: The project aims to reduce losses in the internal network, increase the quantity of drinking water in the village, separate agricultural water from drinking water, and bill the quantities of water consumed. Project Status: completed Start Date: 2021-08-01 ُEnd Date: 2022-11-01 Cost of Project: 241851.43 $ Benefited from project: 800 Supporting entities: Water Authority Budget Classification: Water
Project Components: Construction of 620 m of 3-inch main lines, 1,800 m of 2-inch insulated steel, 2,450 m of house connections, and 135 water meter installations.