Project Name : replace Nahaleen water transmission pipline
Project Description : construction of transmission pipline between 4-12 inches diameter and 11 kms long
Project Category : Water line
Project Goal : increasing quantity of potable water to service areas and reducing water loss in Bethlehem areas-Nahaleen, Hussan, Battir, and Wadi Fokeen
Beneficiary associations : Nahalin,Husan,Wadi fukin,Bter 21673 inhabitants
Cost : 12,214,885$
The sponsor : United States Agency for Development
Completion rate : 100%
Date : 11/6/2013- 19/9/2015
Project Status : completed