City: Nablus Project Goal: The project aims to reduce water loss in the internal network, increase the quantity of drinking water in the village, and rehabilitate new house connections. Project Status: completed Start Date: 2021-12-01 ُEnd Date: 2022-11-01 Cost of Project: 445714.29 $ Benefited from project: 2000 Supporting entities: Water Authority Budget Classification: Water
Project Components: Construction of 3" main lines with a length of 900 m, 2" lines with a length of 4,000 m, and 1" lines with a length of 2,600 m, and house connections.