City: Tulkarem Project Goal: Construction of 10" and 8" diameter main sewer lines to connect some neighborhoods in the village to the main sewer network and the elimination of cesspits. Project Status: completed Start Date: 2022-12-01 ُEnd Date: 2023-07-01 Cost of Project: 495371.71 $ Benefited from project: 700 Supporting entities: Water Authority Budget Classification: wastewater
Project Components: Construction of 10" diameter main sewer lines, 477 meters long, and 8" diameter and 2,630 meters long.