Project Goal: Increasing the quantity of potable water, distributing it fairly, and connecting all homes to the water network in the Shuyukh area. Project Status: under implementaion Cost of Project: 1217142.86 $ Benefited from project: 11280 Supporting entities: Water Authority budget
Project Components:
It includes three phases.
1. The first phase of the project was completed, including the implementation of water pipes of various diameters.
2. The second phase was completed and included: replacing a section of the transmission line supplying the sheikhs with steel pipes of various diameters. 300 mm, 238 meters long + construction of water lines of various diameters.
3. Phase Three: This includes replacing a section of the transmission line with 12-inch diameter pipes and some other work on the transmission line.