City: Hebron Project Goal: Eliminating the impact of wastewater flowing along citizens' lands and homes along a 14.5-km stretch, and protecting agricultural lands and infrastructure from the effects of rainwater flooding. Project Status: under implementaion Start Date: 2021-02-01 ُEnd Date: 2025-01-01 Cost of Project: 9142857 $ Benefited from project: 120000 Supporting entities: Water Authority Budget Classification: wastewater
Project Components: Establishing a line to transfer excess sewage from the wastewater treatment plant and the sewage of the future city of Yatta and the sewage of Al-Fawar camp, and establishing stormwater drainage culverts in Yatta and Beit Amra. The second phase of the project has been completed and the initial acceptance committee has been formed and work is underway in the acceptance process according to the rules. As for the first phase, due to the financial situation, 5 km of the project, which is 6,250 m long, have been completed and work is underway to complete the remaining work.