City: Jenin Project Goal: Establishment of a separate stormwater drainage system to protect the pumping station, treatment plant, and sewage manholes from flooding resulting from rainwater entering the sewage system. The second phase of the project also includes the reuse of treated wastewater. Project Status: under implementaion Start Date: 2022-01-01 ُEnd Date: 2025-01-01 Cost of Project: 1161142 $ Benefited from project: 2000 Supporting entities: AFD Classification: wastewater
Project Components: The project includes the following components:
1. A contract for the second phase: the reuse phase.
2. A consulting contract for the design and supervision of the second phase.
The first phase of the project has been completed, and the project is currently in the evaluation phase to assess the efficiency of the implemented system and determine the feasibility of implementing the second phase based on data on the ground.