Project Goal: Constructing 6" and 8" diameter main sewage lines to connect some neighborhoods in the village to the main sewage network and eliminating cesspits. Project Status: under implementaion Start Date: 2023-05-01 ُEnd Date: 2025-05-01 Cost of Project: 511142.86 $ Benefited from project: 1500 Supporting entities: Water Authority Budget Classification: wastewater
Project Components: • 8-inch diameter transmission line, 976 meters long
• 6-inch diameter sewer lines, 1,720 meters long
• Supply and installation of 105 inspection chambers